Project · PRJ-7005
Hyderabad Adventure Park
Shamirpet, Hyderabad · Turnkey · Project Manager A. Bose · Lead Engineer D. Kamat
Lifecycle stage
- Kickoff
- Engineering
- Customer Approval
- Procurement
- Manufacturing
- QC
- Packing
- Dispatch
- Installation
- Commissioning
- Handover
Contract value
$1,270,000
Contract on file
Estimated / budget cost
$968K
Budget $972K
Actual cost to date
$921K
Forecast $964K
Forecast margin
24.1%
Quoted 23.8% · variance 0.3%
Project data card
- Customer
- WonderSplash Water Park
- Site
- Shamirpet, Hyderabad
- Execution type
- Turnkey
- Planned window
- 2025-10-14 → 2026-09-10
- Schedule variance
- 2 days
- Retention
- —
- Warranty
- —
- Bank guarantee expiry
- —
Cost head: estimate vs actual
Traceability chain
Customer → quotation → contract → project → asset
Customer — WonderSplash Water Park
CUS-1003
Hyderabad, India
Quotation QTN-5502
Won
Estimation → approval → customer acceptance
Contract CTR-9005
—
Contract archive
Engineering release
1 drawings
GA → structural → hydraulic → electrical
BOM & MRP
Rev linked to drawing rev
Multi-level BOM drives material requirement
Procurement
0 purchase orders
RFQ → PO → GRN → incoming QC
Production
2 production orders
FRP, steel, assembly, electrical
Quality
1 inspections
Gate-wise inspection records
Packing & dispatch
0 packages
Packing list, labels, export documents
Installation & commissioning
2 daily site reports
Site progress, safety and handover
Engineering & drawing revisions
| Drawing | Title | Discipline | Rev | Status | Pending |
|---|---|---|---|---|---|
| DWG-6107 | Wave pool — commissioning layout | Hydraulic | Rev C | Customer Approved | 0 d |
Procurement
| PO | Supplier | Material | Qty | Value | Status |
|---|---|---|---|---|---|
| No purchase orders | |||||
Production orders
| Order | Item | Work centre | Progress | Status | Gates |
|---|---|---|---|---|---|
| PO-ASM-3304 | Wave pool caisson assembly | Assembly | 100% | Completed | DWG releasedBOM approved |
| PO-ELE-3305 | MCC panel wiring & FAT | Electrical | 100% | Completed | DWG releasedBOM approved |
Payment milestones
| Milestone | Value | Due | Status |
|---|---|---|---|
| Dispatch (30%) | $381,000 | 2026-06-10 | Paid |
| Commissioning (10%) | $127,000 | 2026-09-20 | Planned |
Risk register
| Category | Risk | Score | Mitigation | Status |
|---|---|---|---|---|
| No open risks | ||||
Change orders, shipments & site activity
DSR-5501 · 2026-08-17 · 18 men88%
Wave pool caisson alignment complete; handrail rework at platform 3.
DSR-5502 · 2026-08-16 · 20 men85%
Pump skid grouting; DN300 header welding 60 m.