VS

Project · PRJ-7001

Dubai Water Park — Phase 2

Jebel Ali, Dubai · Turnkey · Project Manager V. Sharma · Lead Engineer N. Pillai

DelayedPortfolio

Lifecycle stage

  1. Kickoff
  2. Engineering
  3. Customer Approval
  4. Procurement
  5. Manufacturing
  6. QC
  7. Packing
  8. Dispatch
  9. Installation
  10. Commissioning
  11. Handover
62%

Contract value

$3,820,000

Signed 2026-01-22

Estimated / budget cost

$2.9M

Budget $3M

Actual cost to date

$2.2M

Forecast $3.1M

Forecast margin

18.1%

Quoted 24.0% · variance -5.9%

Project data card

Customer
AquaWorld Dubai
Site
Jebel Ali, Dubai
Execution type
Turnkey
Planned window
2026-02-10 → 2026-11-28
Schedule variance
-12 days
Retention
5%
Warranty
24 months
Bank guarantee expiry
2027-03-31

Cost head: estimate vs actual

Traceability chain

Customer → quotation → contract → project → asset

  1. Customer — AquaWorld Dubai

    CUS-1001

    Dubai, UAE

  2. Quotation QTN-5501

    Won

    Estimation → approval → customer acceptance

  3. Contract CTR-9001

    2026-01-22

    $3,820,000 · CIF Jebel Ali

  4. Engineering release

    3 drawings

    GA → structural → hydraulic → electrical

  5. BOM & MRP

    Rev linked to drawing rev

    Multi-level BOM drives material requirement

  6. Procurement

    3 purchase orders

    RFQ → PO → GRN → incoming QC

  7. Production

    2 production orders

    FRP, steel, assembly, electrical

  8. Quality

    4 inspections

    Gate-wise inspection records

  9. Packing & dispatch

    2 packages

    Packing list, labels, export documents

  10. Installation & commissioning

    1 daily site reports

    Site progress, safety and handover

Engineering & drawing revisions

DrawingTitleDisciplineRevStatusPending
DWG-6101Tornado slide — general arrangementGeneral ArrangementRev CReleased For Production0 d
DWG-6102Tower steel structure — fabricationFabricationRev BReleased For Production0 d
DWG-6103Pump room hydraulic schematicHydraulicRev BCustomer Review7 d

Procurement

POSupplierMaterialQtyValueStatus
PO-8801Ashland CompositesIsophthalic polyester resin6000 KG$14,400Partially Received
PO-8802Jindal Steel DepotISMB 300 structural beam22 MT$18,040Delayed
PO-8806Prime FabricatorsPlatform & stair package (subcontract)1 SET$38,400Released

Production orders

OrderItemWork centreProgressStatusGates
PO-FRP-3301Funnel shell segmentFRP
67%
In ProgressDWG releasedBOM approved
PO-STL-3302Tower columns & bracingSteel Fabrication
68%
In ProgressDWG releasedBOM approved

Payment milestones

MilestoneValueDueStatus
Advance (20%)$764,0002026-02-01Paid
Design approval (30%)$1,146,0002026-05-15Paid
Dispatch (30%)$1,146,0002026-10-05Due
Delivery at site (10%)$382,0002026-11-05Planned
Commissioning (10%)$382,0002026-12-15Planned

Risk register

CategoryRiskScoreMitigationStatus
ProductionFRP bowl layup capacity clash with Goa project9Second shift on Mould MLD-114 from week 34.Mitigating
CustomsSASO/Gulf conformity documentation lead time6Pre-shipment inspection booked 3 weeks ahead.Open

Change orders, shipments & site activity

CO-4101 Tornado funnel diameter 18 m → 20 m$242,000Approved
SHP-3403 TGHU-9920117 (40' FR) ×3Jebel AliReady

DSR-5503 · 2026-08-15 · 9 men12%

Foundation setting-out and anchor template check.

INV-9901 Design approval 30%$1,146,000Paid
INV-9902 Change order CO-4101$242,000Overdue

Other projects

Jump across the portfolio