Sign inG

Project Execution

Project Portfolio

Every confirmed contract becomes a project with its own budget, engineering release, production plan, installation programme and profitability.

Portfolio contract value

$0

0 live projects

Forecast cost

$0

Margin 0.0%

Open risks

5

2 scored 9 or above

Change orders in flight

2

Requires approval before execution

Projects

0 of 0 projects — click a project for the full traceability chain

Site snapshot

Multi-lane fibreglass water slide tower installed on site
Installed slide tower photography is attached to each project record for handover documentation and marketing reference.

Project risk register

IDProjectCategoryRiskP × IScoreOwnerStatus
RSK-01PRJ-7001ProductionFRP bowl layup capacity clash with Goa projectHigh × High9Production HeadMitigating
RSK-02PRJ-7001CustomsSASO/Gulf conformity documentation lead timeMedium × High6Export ExecutiveOpen
RSK-03PRJ-7002MaterialVinyl ester resin price escalation 8%High × Medium6Purchase ManagerMitigating
RSK-04PRJ-7003Customer ApprovalGA drawing approval pending 5 days beyond SLAMedium × High6Project ManagerOpen
RSK-05PRJ-7004SiteCrane window limited to 2 nights per weekMedium × Medium4Installation HeadOpen

Payment milestones

ProjectMilestoneValueDueStatus
PRJ-7001Advance (20%)$764,0002026-02-01Paid
PRJ-7001Design approval (30%)$1,146,0002026-05-15Paid
PRJ-7001Dispatch (30%)$1,146,0002026-10-05Due
PRJ-7001Delivery at site (10%)$382,0002026-11-05Planned
PRJ-7001Commissioning (10%)$382,0002026-12-15Planned
PRJ-7002Advance (20%)$328,0002026-04-01Paid
PRJ-7002Design approval (30%)$492,0002026-07-20Invoiced
PRJ-7002Dispatch (30%)$492,0002026-12-01Planned
PRJ-7005Dispatch (30%)$381,0002026-06-10Paid
PRJ-7005Commissioning (10%)$127,0002026-09-20Planned

Change order management

Design, dimension and scope changes with cost, price and schedule impact

IDProjectChangeCost impactPrice impactScheduleStatus
CO-4101PRJ-7001Tornado funnel diameter 18 m → 20 m$186,000$242,000+21 dApproved
CO-4102PRJ-7002Colour change to dual-tone gelcoat, 3 lanes$24,500$31,000+6 dCustomer Approval
CO-4103PRJ-7003Add 2 extra water cannons + interactive feature$18,200$26,400+4 dUnder Review