SurveySiteLeadSurveyorDateAreaCrane accessStatus
SS-3301AquaWorld Dubai, Jebel AliLD-2401M. Iqbal2026-06-188,400 m²FullReport Issued
SS-3302Palm Lagoon, Male AtollLD-2404K. Ravi2026-08-022,100 m²RestrictedCompleted
SS-3303Splash Valley, NairobiLD-2403A. Fernandes2026-08-211,450 m²FullPlanned

Survey detail

Technical findings that constrain design and installation

AquaWorld Dubai, Jebel Ali

Water source
Desalinated municipal + 1,200 m³ balance tank
Power
630 kVA available
Elevation
+3.2 m datum
Constraints
Night-time lifting only; 42 °C ambient design temperature.

Palm Lagoon, Male Atoll

Water source
RO plant, limited buffer
Power
180 kVA (generator backed)
Elevation
+1.1 m datum
Constraints
Barge-only delivery; max package 6.0 m; salt-spray coating spec.

Splash Valley, Nairobi

Water source
Borehole + storage
Power
250 kVA
Elevation
+1,795 m ASL
Constraints
Rainy-season programme risk; import clearance via Mombasa.

Standard survey checklist

Mandatory capture before concept design release

  • Site address & GPS coordinates
  • Available area and plot dimensions
  • Elevation and terrain profile
  • Existing buildings and structures
  • Water source, storage and balance tank
  • Pump room location and drainage
  • Electrical supply and power capacity
  • Access road and transport restrictions
  • Crane accessibility and lifting windows
  • Existing water park equipment
  • Safety constraints and local regulations
  • Climate and environmental design data

Photos, videos, measurements and drawings attach to each line and are compiled into the Site Survey Report.