Delivery Control Tower

Portfolio-wide schedule health, risk register and milestone billing exposure across every live project.

Live projects

6

Order book

$10.1M

Open risks

5

Milestones tracked

10

Risk register

IdProject IdCategoryRiskProbabilityImpactScoreOwnerMitigationStatus
RSK-01PRJ-7001ProductionFRP bowl layup capacity clash with Goa projectHighHigh9Production HeadSecond shift on Mould MLD-114 from week 34.Mitigating
RSK-02PRJ-7001CustomsSASO/Gulf conformity documentation lead timeMediumHigh6Export ExecutivePre-shipment inspection booked 3 weeks ahead.Open
RSK-03PRJ-7002MaterialVinyl ester resin price escalation 8%HighMedium6Purchase ManagerRate contract negotiation with 2 alternate suppliers.Mitigating
RSK-04PRJ-7003Customer ApprovalGA drawing approval pending 5 days beyond SLAMediumHigh6Project ManagerEscalation call scheduled with customer PMC.Open
RSK-05PRJ-7004SiteCrane window limited to 2 nights per weekMediumMedium4Installation HeadModular pre-assembly at yard before lift.Open

Milestone exposure

Project IdNamePctValueDueStatus
PRJ-7001Advance207640002026-02-01Paid
PRJ-7001Design approval3011460002026-05-15Paid
PRJ-7001Dispatch3011460002026-10-05Due
PRJ-7001Delivery at site103820002026-11-05Planned
PRJ-7001Commissioning103820002026-12-15Planned
PRJ-7002Advance203280002026-04-01Paid
PRJ-7002Design approval304920002026-07-20Invoiced
PRJ-7002Dispatch304920002026-12-01Planned
PRJ-7005Dispatch303810002026-06-10Paid
PRJ-7005Commissioning101270002026-09-20Planned