Intelligence
AI Assistant & Management Alerts
Cross-module exception detection over projects, BOMs, procurement, production, quality and finance data.
Active alerts
8
Critical
3
Warnings
4
Modules monitored
12
Lead to AMC
Ask the assistant
Questions answered from live ERP data
Which projects will miss their dispatch milestone this quarter?Summarise margin erosion drivers on PRJ-7001What is the FRP resin shortage exposure for the next 6 weeks?Draft a customer update for the Dubai Phase-3 drawing approval delay
Alert queue
| Id | Severity | Module | Message | Action | Link |
|---|---|---|---|---|---|
| AI-01 | critical | Projects | Dubai Water Park is 12 days behind schedule — funnel layup is the binding constraint. | Approve second FRP shift on MLD-114 | /projects/PRJ-7001 |
| AI-02 | critical | Procurement | ISMB 300 shortage of 32 MT will stop Goa steel fabrication in 9 days. | Release PO to alternate supplier | /procurement |
| AI-03 | warning | Costing | Mumbai project margin has fallen from 24.0% to 17.0% driven by resin escalation. | Review change order pricing | /finance |
| AI-04 | warning | Engineering | Goa GA drawing Rev A has been with the customer for 5 days (SLA 3 days). | Escalate to customer PMC | /engineering |
| AI-05 | warning | Production | FRP resin consumption is 7.8% above standard across 3 batches on MLD-114. | Calibrate catalyst dispenser | /production |
| AI-06 | warning | Sales | Quotation QTN-5502 (Jeddah, $2.78M) has had no follow-up for 7 days. | Schedule follow-up call | /crm |
| AI-07 | critical | Finance | Invoice INV-9902 ($242K, AquaWorld Dubai) is 48 days overdue. | Trigger collection workflow | /finance |
| AI-08 | positive | Logistics | Pune Splash Zone is packed and pre-dispatch QC cleared — ready for dispatch. | Release shipment SHP-3402 | /logistics |