Site Installation & Commissioning

Daily progress reports from site teams, manpower and equipment logs, and the commissioning checklist that gates handover.

Site reports

3

Commissioning checks

5

Checks passed

3

Open punch points

2

Daily site reports

IdProject IdDateWeatherManpowerProgress %Work DoneIssuesSafety Incidents
DSR-5501PRJ-70052026-08-17Clear, 32 °C1888Wave pool caisson alignment complete; handrail rework at platform 3.Customer power supply available only till 18:00.0
DSR-5502PRJ-70052026-08-16Cloudy, 30 °C2085Pump skid grouting; DN300 header welding 60 m.Crane idle 3 hrs awaiting site clearance.1
DSR-5503PRJ-70012026-08-15Hot, 44 °C912Foundation setting-out and anchor template check.Heat-stress work window restricted 12:00-15:30.0

Commissioning checklist

Project IdSystemTestRequiredActualResult
PRJ-7005HydraulicFlow rate at slide entry≥ 240 m³/h252 m³/hPass
PRJ-7005HydraulicHeader pressure2.5-3.2 bar2.9 barPass
PRJ-7005ElectricalEmergency stop response< 2 s1.1 sPass
PRJ-7005StructuralTorque audit — anchor bolts100% sample94% completePending
PRJ-7005OperationalRider dispatch cycle test≥ 480 riders/hrPending