Delivery
Site Installation & Commissioning
Daily progress reports from site teams, manpower and equipment logs, and the commissioning checklist that gates handover.
Site reports
3
Commissioning checks
5
Checks passed
3
Open punch points
2
Daily site reports
| Id | Project Id | Date | Weather | Manpower | Progress % | Work Done | Issues | Safety Incidents |
|---|---|---|---|---|---|---|---|---|
| DSR-5501 | PRJ-7005 | 2026-08-17 | Clear, 32 °C | 18 | 88 | Wave pool caisson alignment complete; handrail rework at platform 3. | Customer power supply available only till 18:00. | 0 |
| DSR-5502 | PRJ-7005 | 2026-08-16 | Cloudy, 30 °C | 20 | 85 | Pump skid grouting; DN300 header welding 60 m. | Crane idle 3 hrs awaiting site clearance. | 1 |
| DSR-5503 | PRJ-7001 | 2026-08-15 | Hot, 44 °C | 9 | 12 | Foundation setting-out and anchor template check. | Heat-stress work window restricted 12:00-15:30. | 0 |
Commissioning checklist
| Project Id | System | Test | Required | Actual | Result |
|---|---|---|---|---|---|
| PRJ-7005 | Hydraulic | Flow rate at slide entry | ≥ 240 m³/h | 252 m³/h | Pass |
| PRJ-7005 | Hydraulic | Header pressure | 2.5-3.2 bar | 2.9 bar | Pass |
| PRJ-7005 | Electrical | Emergency stop response | < 2 s | 1.1 s | Pass |
| PRJ-7005 | Structural | Torque audit — anchor bolts | 100% sample | 94% complete | Pending |
| PRJ-7005 | Operational | Rider dispatch cycle test | ≥ 480 riders/hr | — | Pending |